Building blocks of progress

Reports from Torrelago with 3IA INGENIERÍA

During the month of March, several façades in all apartment blocks where the works were taking place across the district finalised.

In April, most of the façades in blocks from 01 to 05 concluded and the coatings in façades 06 and 07 started. Furthermore, the latticework was installed in blocks 02 and 03.

In May, the coatings were done and the finishes took up to reach the dismantling of scaffoldings in June